SKYLOG contact us client login
about SKYLOG our customers industries FAQ service plans
 
 
 



 

Turner Construction
San Diego Convention Center Expansion Project

The San Diego Convention Center Expansion project was a $216 million expansion and renovation of the existing San Diego Convention Center.  The nation's leading general builder and construction management company, Turner Construction Company, was the design construction manager for this project. Turner’s local office in San Diego is Golden Turner Construction Company which together with architects Tucker, Sadler & Associates and HNTB, the team completed the more than 902,000 square foot expansion in late 2001. This complex project demanded careful, accurate documentation and constant communication among the entire project team. Turner chose to use SkyLog as a tool to help them achieve their many time-sensitive objectives.

Scope of Work
The San Diego Convention Center Expansion project was comprised of 277,000 sq. ft. of exhibithalls, 60,000 sq. ft. of meeting rooms, 41,000 sq. ft. of ballroom area, 200,000 sq. ft. of pre-function and lobby space, and 280,000 sq. ft. of service and support spaces. 

Construction of Harbor Drive Lowering and the Convention Center Plaza were also incorporated into the scope of this project. The Harbor Drive Lowering project consisted of excavation and lowering of the existing four-lane roadway and adding a landscaped median to allow access to the convention center's subterranean parking structure.  Relocation of major storm drains and utilities were required, along with the construction of a storm water pumping facility. The Plaza project involved extensive architectural site work with large sculptural forms and landscaping of approximately two acres of land adjacent to the expansion site.

"We had our crews working two shifts, seven days a week for the last two and half months of the project," said Ron Rudolph, Director of Operations at Turner Construction. "The ease of recording events and project issues via the phone with SkyLog really streamlined the documentation procedures necessary for a project of this size." With SkyLog, any type of project log entry such as RFIs, Back Charges, Delay Memos, Punchlist items, etc. could be easily recorded. ". . .many times our superintendents either lost track, didn’t have the time or just put writing memos, letters, etc. at the bottom of their priority list," said Ron Rudolph. "With SkyLog, there are no excuses. Documentation is time and date stamped for future use and the correspondence is ready for the user’s review by the end of the day."

Notice to Proceed
In September of 1998, Turner began site demolition and utility removal in preparation for the installation of the foundation work.  The foundation area covers approximately 12 acres of the 15-acre site.

$31.5 Million For Steel Phase of the Expansion
The first piece of structural steel for the expansion of the San Diego Convention Center was erected on the construction site July 9, 1999.  The raising of this first piece, a 44' high steel brace frame, represented a major milestone for the expansion project.  When the $31.5 million steel phase of the expansion project was completed in April 2000, over 12,000 separate pieces of steel, weighing some 36 million lbs., had been erected.

Additional Phases No Small Task
Initial construction included the relocation of major public utilities currently running throughout the site such as electrical, storm drain, natural gas, water, cable television and telephone utilities to allow the installation of the building's foundations.  Demolition of the existing single story building, a three-story concrete stair and an adjacent 13-acre asphalt/concrete paved parking lot cleared the site for the new building.

Office and Field Connected In Real Time With SkyLog
With 20 superintendents overseeing various facets, Turner needed a real-time way to capture urgent messages and document subcontractor performance. "It was critical that messages were captured at the job site, documented, picked up by the office, and forwarded via e-mail or fax to the subcontractors that were affected," said Ron Rudolph. "SkyLog worked great for our team on this job."

 
Home | Contact | Login | About SkyLog | Customers | Industries | Faqs | Price & Coverage | Terms of use

Copyright © 2006 All Rights Reserved.
Pacific DataVision Inc.